Carrington Business Park

Introduction

Make an Enquiry

Value: £2.5m
Timeline: 2020 – 2021
Client: Himor
Contract Conditions: NEC Option A

Project Description: Emico's work at the new Himore Carrington development in Manchester involved the installation the high voltage supplies and associated pilot cabling.

Open Gallery

Design and delivery detail:

  • Substation works
  • High voltage supplies
  • Associated pilot cabling
  • Terminations
  • High voltage equipment and supply including UPS and transformers
  • Instrumentation cabling
  • Fibre optic works
  • Telecom cabling
  • Network cabling
  • CMS

Client Key Issues: Himor required a short timeframe for power to be enabled on site therefore Emico substantially reduced the program time for HV installation.
Client Benefits: Client was therefore able to power their construction works and development of parts earlier than would have otherwise been possible. 