Government Project - Cabling
Introduction
Make an EnquiryValue: £1.6m
Timeline: 2019 - 2019
Client: Parliament UK
Contract Conditions: NEC Option A
Project Description: Emico completed the installation of nearly 50,000 metres of Fibre Optic cables throughout the Parliamentary Estate in Westminster. The project is the first phase of the Parliamentary Estate Data Interconnectivity which involves the linking of the Parliament Estate via Fibre Optic cables. The works present a cross-estate ICT infrastructure to support the Digital Services LAN deployment strategy to support the Data Centre move. The works interfaced with the Northern Estate Programmes. The two new 'Primary' LAN core locations are created in close proximity to the Estate.
Open GalleryDesign and Delivery Detail:
Client Key Issues: Highly constrained site requiring careful planning
Client Benefits: No operational impact to parliamentary buildings, staff or obstruction to the general public