Slade Green

Introduction

Make an Enquiry

Value: £600k
Timeline: Oct-Dec 2017
Client: Costain
Contract Conditions: NEC Option A

Project Description: Emico carried out M&E enabling works and design necessary to modify the existing depot M&E services and the installation of new M&E services which included CMS, Small Power and Lighting, Distribution, Service Taps, Trace Heating and Earthing. All the works were carried out within a live and operational environment at a busy rail depot and sidings. The Programme of works were extremely tight, but a robust design ensured the quick and safe delivery with full sign off and handover complete within one week from the construction teams leaving site

Open Gallery

Design & Delivery Detail:

  • Design for M&E including full surveys within operational depot
  • Integrated design with P-Way, Civils, DC Power and Controls
  • Permanent installation of electrical and mechanical
  • Worked as integrated team with Network Rail and Costain
  • Test and Commissioning
  • Handover Packs and Client Training

Client Key Issues: Deliver to an ambitious programme whilst maintaining full operational service within the depot and sidings
Client Benefits: “This is the best M&E design I have ever seen. The clarity of the drawings demonstrates exactly what was required and you have produced practical and buildable solutions” - Costain PM Karin Jones

Back to Projects
Next Project
Lillie Bridge Depot