Value: £1m
Timeline: 2019 – 2020
Client: Spencer Group
Contract Conditions: N/A

Project Description: Existing Down Hertford Loop into Stevenage Station and provide a turnback facility serviced by a new single face platform (Platform 5). To facilitate the extension and adaption of the Platform 5, Signalling and Power had a requirement to upgrade and install new Location Cabinets.

Open Gallery

Design & Delivery Detail:

  • Installation of new Location Cabinets for 650v power
  • Installation of new cabling from relay rooms to Loc’s
  • New platform 5 switchroom
  • Installation of lighting columns.
  • Installation of illuminated handrail
  • Design and installation of fire alarm system, with Vesda system in lift shaft
  • Develop –Testing & Commissioning Plans

Client Key Issues: Working around live stations and re-routing overhead lines.
Client Benefits: Development of Integrated Working Groups with Emico Ltd.