Victoria Dock Portal

Introduction

Make an Enquiry

Value: £4.7m
Timeline: 2015 – 2019
Client: Taylor Woodrow / Vinci

Project Description: Providing a gateway into the tunneled section of the Elizabeth Line. Emico completed the MEPH fit out of the Head House, shaft, and emergency Intervention / escape platform.

Design & Delivery Detail:

  • Fire Main (CDFM), Domestic Water, HVAC, and Sanitary Systems
  • LV, Fire Alarm, SCADA interface & Access Control
  • Pumped drainage duty and standby pumps capable of delivering 108 liters a second at 23.5m head
  • Temporary Works Design.
  • LV/MCC & UPS Switchboard installation
  • Development and implementation of Testing & Commissioning Plans
  • Train the Trainer packs and presentations handover to RFL

Client Key Issues: A tight space, and limits on noise to protect local residents, meant the works presented logistical challenges. Critical Systems Integration.
Client Benefits: The Head House building was the first element of the Crossrail programme to be handed over in August 2019.